Consolidation of DN 58A km 1-24 and km 29-41
- Contract name and description
Consolidation of DN 58A km 1+500 - 24+000 si km 29+000 – 41+382, in association with Genesis International SA
- Contract date and number
- No./ Date: 2043 / 01 July 2008
- Client name and location
- DRDP Timisoara
- Contract period
- Starting date: July 2008
- Status: 100%
- Ending date: April 2009
- Location
- DN 58 A